In Oracle Integration Cloud (OIC), tracing levels control how much execution information is captured for an integration instance. The three levels are:
| Tracing Level | Data Retention | What is Logged | When to Use |
|---|---|---|---|
| Production | 32 days | Logs the integration flow/actions with limited payload logging | Normal production operation |
| Audit | 8 days | More detailed tracing, including external payloads | Troubleshooting and monitoring |
| Debug | 24 hours | Most detailed tracing; logs all actions, including actions inside loops | Detailed troubleshooting/development |
1. Production
Production is the normal/default level for production integrations.
- Execution data is retained for 32 days.
- Logs the overall integration flow/actions.
- Provides less detailed information than Audit or Debug.
- Suitable when the integration is running normally.
- Logs only Invoke/logger actions
Short answer:
“Production tracing is used for normal production execution. It retains execution data for 32 days and provides basic flow-level logging without the detailed payload information available in higher tracing levels.”
2. Audit
Audit provides more detailed information than Production.
- Execution data is retained for 8 days.
- Logs the same flow-level information as Production.
- Also provides external payload logging, which is useful when troubleshooting data exchanged with external applications.
Short answer:
“Audit tracing is mainly used for troubleshooting because it provides more execution details and captures external payload information. The data is retained for 8 days.”
3. Debug
Debug is the most detailed tracing level.
- Data is retained for only 24 hours.
- Provides the same information as Audit.
- Additionally logs all actions within loops, making it useful for detailed troubleshooting.
- Because it generates much more execution information, it should generally be used temporarily.
Short answer:
“Debug tracing provides the highest level of execution detail. It logs actions inside loops in addition to the Audit-level information, but the data is retained only for 24 hours.”
Quick way to remember
Production → Audit → Debug
32 days → 8 days → 24 hours
Less detail → More detail → Maximum detail
How to change the tracing level
From the OIC Console, you can modify tracing for an integration without changing the integration design:
Integration → Actions/Options → Configure → Modify Tracing Level
So, if an interviewer asks:
“How would you troubleshoot an OIC integration that is working in Production but you cannot see enough execution details?”
“To troubleshoot temporarily increase the integration's tracing level from Production to Audit or Debug depending on the required level of detail. And reproduce the issue, analyze the instance activity and payload information, and then reduce the tracing level after troubleshooting.”